7/06/2009 02:28:00 AM

Gantt Chart of the project

Posted by In Tech Corp.



Activities
A. Recruit group member - 1day
B. Set up a blog and update the blog weekly - 4days
C. Research on coding tools - 7days
D. Prepare a proposal - 7days
E. Design a project planning diagram and a Gantt Chart - 7days
F. Coding the application -14days
G. Sent the coding to lecturer to get feedback - 1day
H. Re-contracture the coding - 14days
I. Sent the coding again to get feedback from lecturer - 1day
J. Test and finalize on our developed application and document -7days
K. Write a final technical report to describe the features of software system -7days
L. Present our application to lecturer -7days
M. Submission of project final technical report -7days

-by Wong Chii Lok-

2 comments:

SLBY said...

AOA network diagram ler?

In Tech Corp. said...

uploaded. Going to upload the lifecycle model soon.=)

Post a Comment